Our 50 Bed Halfway House For Men Construction Project

Page 1 (Newest) -- Page 2 -- Page 3 -- Page 4 (Older Entries)


Week of November 9, 2015


Pictures of the completed stairs and railings in the new stair tower.

Completed Stairs



Week of November 2, 2015


Shown is progress on the brick and new stairs for the new stair tower on railroad ave side of building or west end of building.

410 Building Stairwell - Brick Work



Week of October 26, 2015


The window installation has been completed with the aluminum trim and caulking.

Page 1 (Newest) -- Page 2 -- Page 3 -- Page 4 (Older Entries)="/images/large/IMG_3083-large.JPG"/>
410 Building Exterior Showing Progress on Windows



Week of October 19, 2015


First picture is the completed structural walls of the stair tower to the third floor. Next will be roof and bricks to complete the walls of the tower.
Second picture is one of the 3 HVAC units that are completed on the 2nd floor. These units have been tested and work. Next week the 3rd floor HVAC units will be completed.

Completed Stair Tower Wall



Week of October 12, 2015


The west end stair tower has been built from the foundation to second story. Once completed to the third floor, steel and concrete stairs will be installed. This will be the second point of egress to comply with fire and building code.

West end stair tower.



Week of October 5, 2015


Progress continues on the stairwells. The stairs going from the first to second floor have been completed as seen in the picture below. The second floor to third floor stairs are in place and welded, more support beams need to be installed before concrete can be poured.

Stairwell looking up from 2nd to 3rd floor.



Week of September 28, 2015


All though it does not look like much it was a lot of work and coordination to get the first floor to second floors stairs started. Walls were moved floors and beams were cut and the base and rails are finally installed. This weekend final adjustments and welding will begin.

Stairwell under construction.



Week of September 21, 2015


Pictured here The Straight and Narrow(S&N) 50 bed Men's Halfway House (HWH) is half finished. Drywall will be going up over the next two weeks followed by the suspended ceilings, a new stair tower and stairs, priming and painting through the end of October. We will have a lot to be thankful for on Thanksgiving as in November the flooring will be installed, trim work and punch work done. We plan to open before Christmas.
Current View of 2nd Floor From Train Tracks To Straight St.