Week of November 9, 2015
Pictures of the completed stairs and railings in the new stair tower.
|
Completed Stairs
|
Week of November 2, 2015
Shown is progress on the brick and new stairs for the new stair tower on railroad ave side of building or west end of building.
|
410 Building Stairwell - Brick Work
|
Week of October 26, 2015
The window installation has been completed with the aluminum trim and caulking.
|
Page 1 (Newest) -- Page 2 -- Page 3 -- Page 4 (Older Entries)="/images/large/IMG_3083-large.JPG"/>
410 Building Exterior Showing Progress on Windows
|
Week of October 19, 2015
First picture is the completed structural walls of the stair tower to the third floor. Next will be roof and bricks to complete the walls of the tower.
Second picture is one of the 3 HVAC units that are completed on the 2nd floor. These units have been tested and work. Next week the 3rd floor HVAC units will be completed.
|
Completed Stair Tower Wall
|
Week of October 12, 2015
The west end stair tower has been built from the foundation to second story. Once completed to the third floor, steel and concrete stairs will be installed. This will be the second point of egress to comply with fire and building code.
|
West end stair tower.
|
Week of October 5, 2015
Progress continues on the stairwells. The stairs going from the first to second floor have been completed as seen in the picture below. The second floor to third floor stairs are in place and welded, more support beams need to be installed before concrete can be poured.
|
Stairwell looking up from 2nd to 3rd floor.
|
Week of September 28, 2015
All though it does not look like much it was a lot of work and coordination to get the first floor to second floors stairs started. Walls were moved floors and beams were cut and the base and rails are finally installed. This weekend final adjustments and welding will begin.
|
Stairwell under construction.
|
Week of September 21, 2015
Pictured here The Straight and Narrow(S&N) 50 bed Men's Halfway House (HWH) is half finished. Drywall will be going up over the next two weeks followed by the suspended ceilings, a new stair tower and stairs, priming and painting through the end of October. We will have a lot to be thankful for on Thanksgiving as in November the flooring will be installed, trim work and punch work done. We plan to open before Christmas.
|
Current View of 2nd Floor From Train Tracks To Straight St.
3rd Floor standing at elevator facing Straight St.
2nd Floor standing at elevator facing Straight St.
3rd Floor prior to demolition
2nd Floor standing at elevator facing Railroad Ave.
|
Page 1 (Newest) -- Page 2 -- Page 3 -- Page 4 (Older Entries)
|