Our Completed 50 Bed Halfway House For Men Construction Project

Page 1 (Newest) -- Page 2 -- Page 3 -- Page 4 (Older Entries)


Halfway House Opening Ceremony

Governor Christie On Drug Court: No Numbers Can Calculate The Positive Effect On Society



3/31/2016 - NorthJersey.com - Christie attends opening of new Paterson drug treatment facility - Read Full Article

3/31/2016 - The Tribune - Christie attends opening of new drug treatment facility - Read Full Article

4/7/2016 - The Beacon - Straight & Narrow expands services to the addicted - Read Full Article

Click To View Photo Gallery




Week of June 20, 2016


It won't be long now, as we have had all of our inspections and expect to receive our license as we move towards July 1!!!!

Our largest bedroom, comfortable, bright and airy!



Week of April 4, 2016


Offices are being furnished and installation of computers has begun.

Office with desk and computer installed.



Week of March 28, 2016


Certiticate of Occupancy has been issued. Opening ceremony this week, check back next week for pictures of the completed project!

Certificate of Occupancy



Week of March 21, 2016


Furniture assembly and window blinds installation started this week.

Assembled Beds

Week of March 14, 2016


Ceilings have been completed and the final fire inspection was completed and fire permit issued.

Completed Ceilings and fire sensors.



Week of March 7, 2016


Moving in to the home stretch, many rooms are complete and final finish touches are being completed!

A completed room.



Week of February 29, 2016


Floors are now complete, bathroom partitions and showers have also been completed.

Completed floors.



Page 1 (Newest) -- Page 2 -- Page 3 -- Page 4 (Older Entries)
 