Halfway House Opening Ceremony |
Governor Christie On Drug Court: No Numbers Can Calculate The Positive Effect On Society
3/31/2016 - NorthJersey.com - Christie attends opening of new Paterson drug treatment facility - Read Full Article
3/31/2016 - The Tribune - Christie attends opening of new drug treatment facility - Read Full Article
4/7/2016 - The Beacon - Straight & Narrow expands services to the addicted - Read Full Article
Click To View Photo Gallery
|
|
Week of June 20, 2016
It won't be long now, as we have had all of our inspections and expect to receive our license as we move towards July 1!!!!
|
Our largest bedroom, comfortable, bright and airy!
|
Week of April 4, 2016
Offices are being furnished and installation of computers has begun.
|
Office with desk and computer installed.
|
Week of March 28, 2016
Certiticate of Occupancy has been issued. Opening ceremony this week, check back
next week for pictures of the completed project!
|
Certificate of Occupancy
|
Week of March 21, 2016
Furniture assembly and window blinds installation started this week.
|
Assembled Beds
|
Week of March 14, 2016
Ceilings have been completed and the final fire inspection was completed and fire permit issued.
|
Completed Ceilings and fire sensors.
|
Week of March 7, 2016
Moving in to the home stretch, many rooms are complete and final finish touches are being completed!
|
A completed room.
|
Week of February 29, 2016
Floors are now complete, bathroom partitions and showers have also been completed.
|
Completed floors.
|