Our 50 Bed Halfway House For Men Construction Project
Page 1 (Newest) -- Page 2 -- Page 3 -- Page 4 (Older Entries)
Week of February 22, 2016
Things are progressing quickly, ceilings are near completion. All doors are hardware have been installed.
|
Ceilings nearing completion, and installed doors.
|
Week of February 15, 2016
All ceiling grids, vents and returns have been installed. Installation of sprikler heads has started. Flooring has been installed in all rooms and has started in the hallways.
Door and window frames have been installed and door installation has started. All exit signs have been installed and lighting installation is in progress. In the bathrooms, toilets
have been installed and dividers ordered in addition to showers being installed.
|
Ceiling grids, vents and tiles being installed.
|
Week of February 8, 2016
Tile installation has been completed in t he commercial kitchen and tile has been started in the showers.
|
Installed tile in the bathroom shower
|
Week of February 1, 2016
The walls are being primed for paint and the tile floors have been installed in the bathrooms.
|
Installed Tile Floors In Bathroom
|
Week of January 25, 2016
Tiling is ready to begin in the bathrooms and painting is to begin in the rooms.
|
Room Ready For Paint
|
Week of January 18, 2016
All required rough inspections passed! Stayed tuned for next weeks progress update.
|
Passed Inspection stickers.
|
Week of January 11, 2016
Work continues on the elevator with the elevator cab being assembled and installed.
|
Elevator cab assembled
|