Week of December 28, 2015
Work continues on the elevator shaft with drywall and the pit ladder being installed and insulation is being installed in the walls.
|
Elevator shaft sheet rock installation
|
Week of December 21, 2015
This weeks photos show the insulation being installed.
|
Installation of wall insulation
|
Week of December 14, 2015
First phase of sheetrock installation has begun.
|
Room with sheetrock installed
|
Week of December 7, 2015
This weeks photos show 800 boards of Sheetrock being delivered. On Monday, 12 men will begin installation.
|
800 boards of Sheetrock being delivered
|
Week of November 30, 2015
Work continues on the installation of the Elevator, the Elevator platform, piston and rails have been installed.
|
410 Building Stairwell Roof
|
Week of November 23, 2015
Shown is progress on the stairwell roof and roofing materials on new stair tower
|
410 Building Stairwell Roof
|
Week of November 16, 2015
The 410 elevator installation has begun. This is the main shaft and piston being installed.
|
Main elevator shaft.
|